construction
Mechanic engineering (solids & heat branch) are the main special apply to project construction (for example: Fabrication & Erection, Alignment, pre-commissioning and commissioning):
General construction
– Mobilization
– Civil – Mechanical (Mechanic,Piping,Electrical ,Instruments ,Insulation)
– Pre-commissioning & commissioning.
Mobilization:
– Prepare administration building & facilities
– Prepare shop (fabrication, welding, piping, paint & sandblast, insulation, etc)
– Prepare ware house (tools & device, etc)
– Prepare crane & machinery equip & vehicle
Civil works:
All civil works including excavation, concrete foundation, back filling, steel structure
To Construction of industrial and residential buildings with relevant HVAC facilities.
– Access paths
– Concrete works (building & equipment foundation, trenches, etc)
– Building
– Steel structure (fabrication , erection , paint & sandblast , touch up)
– Architecture works
– Paving
– Miscellaneous works
Mechanical:
Mechanic
– Material request & control (Rotary equip : motor & pumps, agitator, fans, fan
blowers, compressor & etc — static equip : vessels, ex-changer, drums, bag
filter, tank & silos & etc — package : dryer , bagging machine, main
compressor, cooling tower & etc) .
– Technical office (equipment drawing control, equipment foundation control,
erection inspection, construction procedure & etc).
– Survey, Foundation hand over
– Prepare equipment erection (foundation prepare, cleaning , chipping &
padding)
– Equipment erection (orientation, position)
– Equipment alignment (static equip : leveling , plumb ness ٌ rotary equip:
leveling , first alignment , second alignment , final alignment)
– Storage tanks (S. S & C.S) & S.S silos (fabrication at site).
– Miscellaneous works
Piping:
– U/G (under ground) piping & A/G (above ground) piping
– Pipe support fabrication & installation
– S. S (Stainless Steel & C.S (Carbon Steel) piping
– Test package
Electrical & Instrument:
Construction and erection of electrical and instrumentation and process control equipment
– Support & ladder & erection
– Cable laying
– Calibration & testing of instruments
– M.C.C & control panel
Paint & insulation:
– Sandblast
– Primary & intermediate & final coat
– Vessels & piping insulation
Pre-commissioning & commissioning:
Pre-commissioning test and commissioning of all types of industrial machineries and equipment with process control systems.
Prepare planning & time schedule & man powers estimated. (Around 100 qualified people as a potential task force)
Mechanical completed (remaining works)
Alignment & accessories erection & equipment control
– Electrical & instrument completed (remaining works)
– Calibration & testing of instruments
– M.C.C & control panel
– Single start (free run or unload start) from power substation.
Test time: 8 hours continues with PLC (power logic control) from C.C.R
(central control room)
– loaded start or group start (test and start with loading)
Test time: 8 hours continues with PLC (power logic control) from C.C.R
(central control room)
– Department test and start (package test and start) step by step
– Area & sub area test
Test time: 48 hours continues with PLC (power logic control) from C.C.R (central
control room)
– Area test and start (with process from C.C.R with PLC (power logic
control)
Test time: 168 hours continues (one week)